William F. Moore Park Reconstruction
-
100% complete
-
100% complete
-
4% complete
This project will reconstruct William F. Moore Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2021
Projected Completion Date:
December 2022
Completion Date:
May 2023
Procurement
Start Date: May 2023
Projected Completion Date:
April 2024
Completion
Date:
January 2025
Construction
Start Date: February 2025
Projected Completion Date:
February 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
William F Moore Park, Queens
Corona Avenue, 51st Avenue, 108th Street
Community Board: 04
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 04/18/2025