Sara D. Roosevelt Park Rivington Street Playground Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Rivington Street Playground at Sara D. Roosevelt Park.

Project Notes

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Assigned & Start Date: December 2021
Projected Completion Date: March 2023

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • City Council

Location

Sara D. Roosevelt Park, Manhattan
Rivington Street between Chrystie Street and Forsyth Street
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 04/18/2025