Sara D. Roosevelt Park Rivington Street Playground Reconstruction
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct Rivington Street Playground at Sara D. Roosevelt Park.
Project Notes
Project Update: All contract documents are now in final review to complete the design process.
Project Timeline
Design
Assigned & Start Date: December 2021
Projected Completion Date:
March 2023
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Sara D. Roosevelt Park, Manhattan
Rivington Street between Chrystie Street and Forsyth Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 04/18/2025