Riverside Park Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct a seawall along the Hudson River at West 97th Street in Riverside Park.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

NYC Parks staff members are currently reviewing the scope of the work order.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: September 2025
Completion Date: March 2025

Procurement

Start Date: March 2025
Projected Completion Date: August 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral