Brooklyn Street Tree Planting FY24 - Community Board 1-4 & 6

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 1-4 & 6 in Brooklyn.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: June 2024
Completion Date: April 2024

Procurement

Start Date: April 2024
Projected Completion Date: August 2025
Completion Date: April 2025

Construction

Start Date: March 2025
Projected Completion Date: March 2027

Understand how we build parks.

Funding

Total Funding: $8,400,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 04/18/2025