Annadale Green Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the passive park and sidewalks at Annadale Green.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2023
Projected Completion Date:
January 2024
Completion Date:
January 2024
Procurement
Start Date: January 2024
Projected Completion Date:
September 2025
Completion
Date:
April 2025
Construction
Start Date: April 2025
Projected Completion Date:
April 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Annadale Green, Staten Island
Jefferson Boulevard and Annadale Road
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 04/18/2025