Citywide Tree Rescue FY22

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    16% complete

This project will perform tree rescue work, such as pruning, soil decompaction, expending tree pits, removing debris, removing metal tree guards and grates.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: December 2022
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: January 2023
Completion Date: December 2024

Construction

Start Date: January 2025
Projected Completion Date: January 2027

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Various locations, citywide

Project Staff

Contact NYC Parks about this project

Last updated: 04/18/2025