Citywide Tree Rescue FY22
-
100% complete
-
100% complete
-
16% complete
This project will perform tree rescue work, such as pruning, soil decompaction, expending tree pits, removing debris, removing metal tree guards and grates.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
December 2022
Completion Date:
May 2022
Procurement
Start Date: May 2022
Projected Completion Date:
January 2023
Completion
Date:
December 2024
Construction
Start Date: January 2025
Projected Completion Date:
January 2027
Understand how we build parks.
Funding
Last updated: 04/18/2025