Greenbelt Recreation Center Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct the basketball courts at the Greenbelt Recreation Center.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: November 2024

Construction

Start Date: April 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $2,500,000
Funding Source: City Council

Location

Blood Root Valley, Staten Island
501 Brielle Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 04/18/2025